Supreme Decree No. 5775 establishes mechanisms to modify certain public works contracts, due to the increase in the prices of construction materials, machinery, equipment, and diesel. It also provides for granting additional advance payments and making payments for materials stored in warehouses.
I. MECHANISMS. –
1. Price adjustment: allows updating the prices of construction materials, machinery, equipment, and diesel in public works contracts.
2. Additional advance payments or payment for materials in warehouses: authorizes payment of up to 80% of the cost of the materials acquired, leaving the remaining 20% for when they are incorporated into the work.
3. Increase in the amount of technical supervision contracts: allows the amount of the contracts to be increased when changes to the work schedule justify it.
II. TO WHICH CONTRACTS DOES IT APPLY?
- Works contracts that do not yet have a notice to proceed.
- Works contracts that are already underway.
- Technical supervision service contracts linked to the works.
- Contracts signed by public entities under the framework of Supreme Decree No. 0181, of June 28, 2009 (NB-SABS).
III. APPLICATION OF THE ADJUSTMENT MECHANISMS. –
4.1 Conditions:
Establishes general conditions that must be observed for the application of the adjustment mechanisms. The identification of the inputs subject to variation and the technical and economic justification of the increases must be taken into account.
4.2 Price adjustment in contracts with an initial term of less than or equal to 540 calendar days:
The adjustment of prices of construction materials, machinery, and equipment that have an impact on the cost of executing the work is authorized. In the case of diesel oil, the adjustment is calculated considering the cost of this input used by the machinery and equipment.
4.2 Price adjustment in contracts with an initial term of more than 540 calendar days:
Implements the use of a polynomial formula that considers up to seven (7) critical inputs to calculate cost variations during the execution of the contract.
IV. BENEFITS. –
- Additional advance payments to acquire materials, machinery, and equipment pending purchase.
- Payment of up to 80% of the cost of the materials by the contracting public entity, which have already been acquired and are stored in warehouses.
V. DISADVANTAGES. –
- Does not apply to private works between individuals.
VI. CONCLUSION. –
This decree constitutes an exceptional measure aimed at providing solutions to the economic difficulties affecting the execution of public works and technical supervision contracts, due to the increase in the prices of construction materials, machinery, equipment, and diesel.
It should be noted that this provision is directed at works contracts and technical supervision services signed by public entities under the Basic Standards of the System for the Administration of Goods and Services (NB-SABS), as well as the special cases provided for in the decree itself. It does not include private construction between individuals.